Faena Forum | Miami Beach, FL


/ SCOPE

Develop, fabricate, pre-assemble and deliver structural, cold-formed metal framing to construct a 70-foot diameter spiral coffered dome within a concrete building shell.

  • Develop a cold-formed metal framing system to replace the originally specified concrete dome

  • Deliver a trussed dome package, assembly instructions with color-coding for efficient installation.

  • Meet specified 2-hour fire rating for dome structural components.

  • Coordinate dome structural capacity with structural anchors for lighting, theatrical and AV equipment.

  • Deliver the full solution in a compressed 9 week schedule

/ SOLUTION

Radius Track used digital laser scans of the concrete shell and structural connection points to develop and fabricate hybrid cold-formed steel/tube steel trusses and framing elements. The entire framing system was designed and sequenced to optimize installation efficiency.

  • Hybrid trusses easily fit through building openings and set in place with chain hoists and scaffolding.

  • Easy to follow installation instructions for each type of framing element in the dome package.

  • Performance designed metal framing delivered to meet the contractors tight schedule.

/ RESULT

Outsourcing the custom fabricated dome framing to Radius Track provided a CONSTRUCTABLE, PERFORMANCE BASED solution that saved the contractor time, allowed them to maximize on-site labor efficiency and met the tight schedule.


/ PROJECT TEAM

  • Architect: OMA

  • General Contractor: Layton Construction Co.

  • Framing & Drywall Contractor: Titus Construction Group

  • Distributor: L & W Supply

  • Cold-formed Steel Framing System: Radius Track Corporation

/ AWARDS

  • 2017 CFSEI First Place Award for Design Excellence

  • 2017 CISCA Construction Excellence Award; Southeast Region, Gold Winner; Category: Ceilings

 

“Radius Track added value and solved technical challenges for the project at every step, from structural, consulting, and fabrication through installation assistance. It seemed as if their Senior Design Technologist was available to us 24/7.”